Reference · Production · Shopfloor transparency

Downtime that finally has a reason

A maker of plastic and metal parts now measures the OEE of its 40 machines live instead of in Excel — with downtime reasons captured at the line and a daily shopfloor meeting that works through the biggest losses.

Baseline level (trend)With live OEE and shopfloor meeting
606570CW 10CW 14CW 18CW 22CW 26CW 28Pilot go-live
OEE in the pilot areas (%, two-week average)
OEE in the pilot areas (%, two-week average)
Baseline level (trend)With live OEE and shopfloor meeting
CW 1061.461.4
CW 1260.860.8
CW 1461.261.2
CW 1660.662.3
CW 1861.364.1
CW 2060.966
CW 2261.567.8
CW 2460.769.2
CW 2661.170.4
CW 286171

Outcome

  • 61 → 71%

    OEE in the pilot areas

    average of the baseline in CW 10–15 versus CW 26–29, calculated per VDMA 66412-1

  • 100%

    machines connected live

    40 of 40: 23 via OPC UA, 11 via protocol converters at the edge, 6 legacy machines via retrofit IO modules

  • 41 → 6%

    unclassified downtime

    share of downtime minutes with no assigned reason in the pilot areas: baseline from the shift log, value eight weeks after go-live

  • 45 → 5 min

    time for the shift report

    per shift; the report is built from machine data, only comments are added by hand

Starting point

The client makes plastic and metal parts for the automotive and electrical industries in three shifts. Around 40 machines of very different ages stand on the shop floor: current injection moulding machines with modern controllers, and eccentric presses from the 1990s with no data interface at all.

Shift leaders transferred OEE from tally sheets into Excel, where it stood at around 74% — a week late. Why machines were down was hard to trace: the most common entry in the shift log was "fault", and production and maintenance regularly reached different conclusions about causes. Ahead of an investment decision on an additional injection moulding machine, management wanted to know how much capacity was left in the existing equipment.

Mandate

Wendix was engaged to connect all machines, report OEE live against a single definition and set up a daily shopfloor routine — first in two pilot areas, then across the plant. Agreed acceptance criteria: all 40 machines with automatic data capture, OEE per VDMA 66412-1 with written definitions, no more than 2% deviation of good-part counts from ERP postings, and at least 90% of downtime minutes classified in the pilot areas four weeks after go-live.

An MES with order control and feedback to the ERP, predictive maintenance and energy monitoring were out of scope. The actions coming out of the shopfloor meeting were implemented by the client's own team; we built the routine and facilitated it in the first weeks.

Approach

Step by step to the result

  1. 01

    Shopfloor analysis and machine survey

    Walk-throughs on all three shifts, conversations with shift leaders, maintenance, production planning and the works council. For each of the 40 machines we recorded the controller, interfaces and available signals, and traced the existing Excel process.

    Deliverable: Connectivity plan per machine, choice of pilot areas and acceptance criteria

    Week 1–2

  2. 02

    Connecting the pilot areas

    An injection moulding cell with eight machines and a stamping line with four presses connected: the injection moulding machines via OPC UA per EUROMAP 77, two newer presses via a protocol converter, two eccentric presses without any data interface via retrofit IO modules for run signal, stroke counter and fault. Edge gateway in its own OT network zone.

    Deliverable: 12 machines connected live, data capture from week 3 — not yet shown at the line

    Week 2–4

  3. 03

    OEE model and downtime reasons

    Agreed with production and controlling what counts as planned production time, where the ideal cycle time comes from and which stops are planned. We aligned the reason catalogue with the Six Big Losses and cut it down at the line, together with the shift leaders, to 24 codes on two levels. We calculated the baseline from weeks 3 to 8 against the agreed definition.

    Deliverable: Written OEE definition, reason catalogue, works agreement on data use and a measured baseline of 61% instead of the 74% in Excel

    Week 4–8

  4. 04

    Pilot go-live and shopfloor routine

    Tablets at the lines, shift boards on large screens, automatic shift report. Every day at 7:45 a 15-minute meeting at the board: top three losses of the last 24 hours, one action each with an owner and a date. We facilitated the meeting for the first six weeks.

    Deliverable: Stable daily routine with an action list, led by the production manager

    Week 9–14

  5. 05

    Rollout and handover

    Connecting the remaining 28 machines, including four more legacy machines via retrofit. Reconciling good-part counts with ERP postings, training shift leaders, handing over operations and catalogue maintenance to maintenance and IT.

    Deliverable: All 40 machines live, runbook and internal owners for data and routine

    Week 13–21

Solution

Architecture and delivery

  1. 01

    Machines

    OPC UA, EUROMAP 77, retrofit IO on legacy machines

  2. 02

    Edge gateway

    buffers and normalises, own OT network zone

  3. 03

    Data platform

    time series, OEE per VDMA 66412-1, ERP master data

  4. 04

    Tablet and shift board

    downtime reason right at the line

  5. 05

    Shopfloor meeting

    top three losses, actions with dates

  • Machine connectivity three ways: OPC UA where the controller supports it, protocol converters at the edge for older controllers, retrofit IO modules for machines with no data interface at all. The edge gateway buffers the data so that no shift data is lost during a network outage.
  • OEE is calculated automatically per machine, shift and order — as availability × performance × quality, with ideal cycle times from cleaned-up ERP master data.
  • For every stop longer than two minutes the tablet at the line asks for the reason, in no more than three taps. Shorter stops are automatically booked as minor stops under performance.
  • Shift boards show target and actual for the running shift and the biggest losses; the shift report is generated automatically and only needs comments.
  • Reporting only at machine and shift level, never per person — set down with the works council in a works agreement. Data platform on a server in the plant, read-only access from the office network.

Technology

OPC UA / EUROMAP 77Edge gatewayRetrofit IO modulesTime-series databaseTablets and large screensERP interface

Methodology

How we worked

OEE per VDMA 66412-1 and ISO 22400

We fix the definitions before measuring: planned production time, ideal cycle time, planned stops. That makes the figure comparable across lines and shifts, and not up for debate.

Six Big Losses

Every loss reason — whether downtime, minor stop or scrap — maps to exactly one of the six loss types and therefore clearly to availability, performance or quality. That turns a percentage into a list of concrete losses.

OPC UA with an edge gateway

A vendor-neutral standard, with the EUROMAP 77 companion specification for injection moulding machines. Where the controller provides nothing, three or four signals via a retrofit IO module are enough.

Network segmentation per IEC 62443

Machines and edge sit in their own OT zone; the gateway is the only crossing into the office network. The machines stay unreachable from outside.

Short interval management

Short, fixed check-ins instead of monthly reports: a handover at the shift board at every shift change, plus the daily meeting with fixed rules — the three biggest losses, one action per loss, a name, a date. Only this routine turns transparency into improvement.

Insights

What we take away

  1. 01The first measured OEE was 13 percentage points below the Excel figure, because minor stops and speed losses had never been recorded. Discuss that with management before the first dashboard goes up — otherwise the tool gets the blame.
  2. 02Just over half of the gain came from availability (78 → 85%), mostly from waiting for material, tooling and first-part approval — not from technical faults.
  3. 03A reason catalogue the line helped design gets used. The original maintenance list of more than 80 codes was simply skipped at the machine.