Out of the server room without stopping production

A mid-sized machinery maker moves 138 VMs from its ageing in-house server room into the AWS Frankfurt region — in six waves, landing zone first, and without unplanned downtime on the shop floor.

VMs migrated (cumulative)
050100150JanMarMayJulSepOctServer room off
Cumulative VMs migrated to the EU cloud (end of month)
Cumulative VMs migrated to the EU cloud (end of month)
VMs migrated (cumulative)
Jan0
Feb2
Mar9
Apr24
May49
Jun82
Jul116
Aug138
Sep138
Oct138

Outcome

  • 138

    VMs migrated to the EU cloud

    of 152 inventoried VMs; 14 retired or replaced by SaaS instead of being moved

  • ≤ 40 min

    planned downtime per critical system

    ERP and MES cut over on a weekend, outside shift hours; no unplanned production stop

  • Week 35

    server room switched off

    three racks, UPS and cooling decommissioned, drives securely erased with certificates

  • 99.95%

    availability of ERP and MES

    measured since cutover, databases across two availability zones instead of on one host

Starting point

The client builds special-purpose machines and assemblies for the automotive and packaging industries. All systems ran in a server room in the office building: 152 virtual machines on four virtualisation hosts, a storage system whose vendor support was running out, and tape backups in the same room. Everything was looked after by a single administrator; cover existed only on paper.

Production cannot do without ERP and MES: without them there are no production orders, no shop-floor confirmations and no shift planning. A cooling failure the previous year had shown how close the company was to a standstill. At the same time, as a machinery manufacturer of this size, the client is an important entity under NIS2 and has to be able to evidence recovery and logging.

Mandate

Wendix was engaged to plan and execute the move to the EU cloud, from assessment to switching off the server room. Agreed acceptance criteria: all production systems in the Frankfurt region, no more than 60 minutes of planned downtime per critical system and only in agreed weekend windows, a tested fallback path for every wave, and guardrails and infrastructure entirely as code.

The OT network and the machine controls on the shop floor were out of scope, as was modernising individual applications into cloud-native services. The latter is planned for a second stage, based on the closing Well-Architected review.

Approach

Step by step to the result

  1. 01

    Inventory and migration strategy

    Agent-based discovery of all 152 VMs over four weeks: utilisation, network connections, dependencies. Together with the business units we made a 7R decision for each of the 36 applications and rated its criticality for production.

    Deliverable: Application portfolio with 7R decisions, dependency map and wave plan

    Week 1–5

  2. 02

    Landing zone

    Account structure for production, test, shared services and logging, a redundant VPN link to the plant, sign-in through the existing Active Directory. Guardrails such as region restriction, mandatory encryption and central logging, entirely as code.

    Deliverable: Accepted landing zone with a Well-Architected review as the baseline

    Week 2–7

  3. 03

    Pilot wave

    Nine low-criticality VMs — test systems, licence server, internal wiki — as a dress rehearsal for the procedure. Replication, test launch, cutover and a deliberately triggered rollback were run through once end to end.

    Deliverable: Proven cutover and rollback runbook

    Week 7–10

  4. 04

    Migration waves 1 to 4

    107 VMs in four waves, grouped by dependencies rather than by department. Databases moved to managed SQL Server with Multi-AZ, file servers to a managed file service. Every wave with a go/no-go meeting and a 14-day fallback window.

    Deliverable: 116 VMs in production in Frankfurt by the end of July

    Week 10–30

  5. 05

    Wave 5: ERP and MES

    The 22 VMs of ERP, MES and their interfaces came last. All 23 interfaces inventoried and tested in two dress rehearsals, latency between the shop floor and Frankfurt measured up front, databases replicated continuously so that only the final sync remained at cutover. Cutover on a weekend without shifts.

    Deliverable: ERP and MES in production in the EU cloud, fallback path kept until sign-off

    Week 26–33

  6. 06

    Decommissioning, hypercare and handover

    Server room switched off in week 35, drives securely erased with certificates, maintenance contracts terminated. Then rightsizing to actual utilisation, a closing Well-Architected review and training for the internal IT team.

    Deliverable: Runbook, cost budget with alerts and a documented handover to internal IT

    Week 33–43

Solution

Architecture and delivery

  1. 01

    Server room

    152 VMs, 36 applications, hardware at end of life

  2. 02

    Assessment

    Inventory, dependencies, 7R per application

  3. 03

    Landing zone

    Accounts, network, guardrails as code

  4. 04

    Migration waves

    Replication, test launch, cutover with rollback

  5. 05

    Operation in Frankfurt

    Monitoring, backup, cost control

  • Landing zone before the first VM: separate accounts for production, test, shared services and logging. Guardrails technically prevent resources from being created outside the EU or stored unencrypted.
  • Continuous block-level replication for every rehost candidate. Cutover happened only after a successful test launch in the cloud; the source VM was then kept shut down but untouched for 14 days as a fallback.
  • Replatform where it simplifies operations: databases on managed SQL Server with automated backups and Multi-AZ, file servers on a managed file service. Eleven VMs were retired; three more were dropped because their applications were replaced by SaaS.
  • Redundant VPN link between the plant and Frankfurt, sized on measured MES latency. Machine-level components stayed on the shop floor so production keeps running if the link goes down.
  • All infrastructure in Terraform with mandatory review, central logging and monitoring, backups copied to a second EU region. This lets the client evidence the NIS2 requirements for logging and recovery.

Technology

AWS Frankfurt regionAWS Application Migration ServiceTerraformManaged SQL Server (Multi-AZ)Redundant site-to-site VPNCentral logging and monitoring

Methodology

How we worked

7R migration strategies

A deliberate decision for each application between retire, retain, rehost, relocate, replatform, repurchase and refactor. Nothing moves to the cloud just because it sat in the server room.

AWS Well-Architected review

At the start for the target architecture, at the end for the running system. Findings across all six pillars go into the backlog, prioritised, rather than into a report.

Migration waves with a rollback plan

Waves cut along technical dependencies, each with go/no-go criteria and a rehearsed way back. That makes weekend cutovers predictable instead of risky.

Landing zone with GDPR and NIS2 guardrails

Region restriction, mandatory encryption, central logging and least privilege as preventive controls. Compliance becomes a property of the platform, not an after-the-fact audit.

Infrastructure as code

Every resource in Terraform, every change reviewed. Environments are reproducible, and the knowledge lives in the repository rather than with a single person.

Insights

What we take away

  1. 01The dependency analysis changed the wave plan more than any technical question: seven applications depended on the ERP through undocumented file shares.
  2. 02Retiring is the cheapest migration. Eleven of 152 VMs were no longer needed — that only became visible through measured usage, not the server list.
  3. 03Demonstrate a rollback once and cutover windows get approved more easily: after the pilot wave, production management scheduled the weekend slots on its own.

Next step

Ready to put digitalization into practice?

Start with a compact digitalization assessment — clearly scoped, no long-term commitment.

Book a conversation